Quantitative Aptitude โ€ข  25 Min Read

Time & Work (Part 1): LCM Efficiency Method, Chain Rule & 10 Core Solved Patterns

Total High Yield MCQs

160+ Questions

Target Assessment

SSC CGL, RRB NTPC, State JE

Difficulty Range

Basic to Advanced Level

------------------------------------------

1. THE MASTER LCM & EFFICIENCY BALANCING METHOD

โœ“ The Inverse Proportionality: Time required to complete a fixed task is always inversely proportional to the individual's structural Efficiency or rate of work (Time = 1 / Efficiency).
โœ“ Total Work Initialization: Instead of dealing with fractional parts like 1/x, calculate the Least Common Multiple (LCM) of all given individual day parameters and assign it as the absolute units of Total Work.
โœ“ Daily Unit Generation: Divide the assumed Total Work units by the specific number of days taken by a person to find their individual absolute single-day efficiency units.
โœ“ Blended Work Framework: When multiple people operate concurrently, add their daily efficiency units directly to solve equations rapidly: Combined Time = Total Work / โˆ‘(Individual Efficiencies).

2. THE MDH CHAIN RULE & ALTERNATE DAY CONFLICTS

โœ“ The Universal MDH Formula: Used for group work configurations involving shifts in group numbers, hours, days, or target work scopes: (M1 ร— D1 ร— H1 ร— E1) / W1 = (M2 ร— D2 ร— H2 ร— E2) / W2.
โœ“ Variable Meanings: M matches the number of active workers; D is the count of operational days; H represents working hours per day; E is the group efficiency scaling parameter; W matches the absolute quantity of target work units.
โœ“ Alternate Day Timelines: When individuals work in rotation (e.g., A on day 1, B on day 2), group the sequential separate steps into combined multi-day blocks (like 2-day or 3-day work cycles) to trace balances safely without fractional conversion error.

3. HIGH-YIELD STEP-BY-STEP EXAMPLES (1-5)

โœ“ Example 1: A can complete a piece of work in 10 days and B can do it in 15 days. In how many days can they complete it together? Solution: Total Work = LCM(10, 15) = 30 units. Efficiency of A = 30/10 = 3 units/day. Efficiency of B = 30/15 = 2 units/day. Combined efficiency = 3 + 2 = 5 units/day. Combined Time = 30 / 5 = 6 days.
โœ“ Example 2: A and B together can do a work in 12 days, while B alone can finish it in 30 days. In how many days can A alone complete the task? Solution: Total Work = LCM(12, 30) = 60 units. Efficiency of (A + B) = 60/12 = 5 units/day. Efficiency of B = 60/30 = 2 units/day. Efficiency of A = 5 - 2 = 3 units/day. Time for A alone = 60 / 3 = 20 days.
โœ“ Example 3: A is twice as efficient as B and can complete a job 30 days earlier than B. In how many days can they finish it working together? Solution: Ratio of efficiencies A:B = 2:1, so ratio of time taken A:B = 1:2. The difference in time units is 2 - 1 = 1 unit. Given 1 unit = 30 days. Hence, A takes 30 days and B takes 60 days. Total Work = 60 units. Combined efficiency = 2 + 1 = 3. Combined Time = 60 / 3 = 20 days.
โœ“ Example 4: If 20 men can build a wall in 15 days working 8 hours a day, how many days will 15 men take to build the same wall working 10 hours a day? Solution: Apply Chain Rule where W1 = W2. M1ร—D1ร—H1 = M2ร—D2ร—H2 => 20 ร— 15 ร— 8 = 15 ร— D2 ร— 10 => 2400 = 150 ร— D2 => D2 = 2400 / 150 = 16 days.
โœ“ Example 5: A can do a work in 20 days and B in 30 days. They start together but A leaves 5 days before the completion of work. Find the total time taken to finish the work. Solution: Total Work = LCM(20, 30) = 60 units. Efficiency of A = 3, B = 2. If A did not leave, he would have done an extra 5 ร— 3 = 15 units. Adjust total work scale: 60 + 15 = 75 units. Total time = 75 / (3 + 2) = 75 / 5 = 15 days.

4. HIGH-YIELD STEP-BY-STEP EXAMPLES (6-10)

โœ“ Example 6: A, B, and C can do a work in 12, 15, and 20 days respectively. How many days will it take if they work on alternate days sequentially starting with A? Solution: Total Work = LCM(12, 15, 20) = 60 units. Efficiency of A=5, B=4, C=3. 1st day (A) = 5 units, 2nd day (B) = 4 units, 3rd day (C) = 3 units. Total work in 1 cycle (3 days) = 5+4+3 = 12 units. Multiply cycles to approach target: 5 cycles ร— 12 units = 60 units. Total time = 5 cycles ร— 3 days = 15 days.
โœ“ Example 7: 12 men or 18 women can finish a task in 14 days. How many days will 8 men and 16 women take to finish the identical work? Solution: Convert elements to find scaling factors: 12M = 18W => 2M = 3W => 1M = 1.5W. Total workforce value in terms of women: 12M = 18W working for 14 days. Target group: 8M + 16W = 8(1.5W) + 16W = 12W + 16W = 28W. Apply direct variation: 18W ร— 14 days = 28W ร— D2 => D2 = (18 ร— 14) / 28 = 9 days.
โœ“ Example 8: A camp has provisions for 150 men for 45 days. After 10 days, 25 men leave the camp. How long will the remaining provisions last for the surviving men? Solution: Balance provisions remaining after 10 days = 150 men ร— 35 days. Remaining count of men = 150 - 25 = 125 men. Apply equation: 150 ร— 35 = 125 ร— D2 => D2 = (150 ร— 35) / 125 = 42 days.
โœ“ Example 9: A can complete a job in 24 days. B is 60% more efficient than A. Find the total time taken by B alone to finish the work. Solution: Efficiency ratio A:B = 100 : 160 = 5:8. Time taken is inversely proportional to efficiency: Time of B = (Efficiency of A / Efficiency of B) ร— Time of A = (5 / 8) ร— 24 = 15 days.
โœ“ Example 10: 4 men and 6 boys can finish a work in 8 days, while 3 men and 7 boys can finish it in 10 days. Find the time taken by 10 boys alone to complete it. Solution: (4M + 6B) ร— 8 = (3M + 7B) ร— 10 => 32M + 48B = 30M + 70B => 2M = 22B => 1M = 11B. Total work in boy units = [4(11B) + 6B] ร— 8 = 50B ร— 8 = 400 units. Time taken by 10 boys = 400 / 10 = 40 days.